NINE YEARS ON V: 2018: THE GARDEN THAT COST A LOT: CLAIMANTS SOUGHT £360,000 – AND RECEIVED NOTHING… EXCEPT A BILL FOR £2 MILLION

A prominent QC tweeted recently that, when he was waiting for a court judgment to be delivered, his greatest fear was that the case would end up in the “Proving Things” series on this blog.  Today we look a post from that series written in 2018. I wrote about the decision in Burges & Anor v Lejonvarn [2018] EWHC 3166 (TCC).  If anything this is case that shows the dangers of a split trial, with issues of law being tried before findings of fact.  Here the matter went to the Court of Appeal upon the issue on the duty of care owed by someone providing services gratuitously.   However, as I said at the time, the decision at trial may be of more significance to anyone planning to practice law.  The claimants’  fundamental difficulty was that they had not suffered any loss.  They claimed £360,000 but recovered nothing.   I have also set out below the subsequent post on the Court of Appeal decision on costs, which added more to the claimants’ difficulties. (It was reported that the costs that the claimants had to pay were some £2 million).

 

THE POST FROM 2018

“Law students have probably already been taught, and will be lectured for generations to come, about the implications of the Court of Appeal decision in Lejonvarn v Burgess & Anor [2017] EWCA Civ 254. If any of those law students plan to go into practice then they need to read the judgment after trial today in Burges & Anor v Lejonvarn [2018] EWHC 3166 (TCC). The claimants in that case may have won the first battles, at the  trial however the demonstrably lost the war.  This is as strong an example of a failure to prove things as you will ever find.  The claimants claimed nearly £360,00 and received precisely nothing.  This is likely to prove an expensive day out for privately funded litigants (or indeed any litigants).

 

I consider that the Claimants could and should have attempted to identify what actual, if any, losses were suffered as a result of the breaches of alleged. To claim that the Defendant is liable for the global claim offends common sense and I find it wholly unsupported by the evidence which I have heard and read.”

THE CASE

The claimants and the defendant were friends and neighbours. The defendant, who had worked as an architect, helped the claimants in the development of a garden.  After the relationship between the parties broke down the claimants brought proceedings against the defendant.  At a trial of a preliminary issue it was held that the defendant owed the claimants a duty of care even though her services were not being provided for reward. That decision was upheld by the Court of Appeal.

THE TRIAL

This was the second trial.  The defendant had ceased to be involved in the development of the garden when there was a dispute over the budget. The claimants’ claimed £359,228.52,  the original budget was £130,000

OUR OLD FRIEND WITNESS CREDIBILITY

The judge considered the question of the claimants’ credibility,  he found that the first claimant’s evidence was unsatisfactory. He “gave a lot of evidence about what he thought the claimant was doing but he was in Majorca for significant periods…”

The judge stated that, except in one respect, “I prefer to accept the Defendant’s evidence supported by the contents of the contemporaneous note which was written when the parties were still co-operating and were still friends.”

THE CLAIMANTS’ “SCATTERGUN” APPROACH

The judge observed that the nature of the claimants’ case had developed over time “Despite this claim having been case-managed by at least eight different full-time or part-time TCC High Court Judges and despite Written Opening and Closing Submissions running in length in excess of 250 pages, the nature of the case advanced against the Defendant is still not clear and the precise breaches of duties alleged against the Defendant are still not clear.”

  • “… the Claimant’s claim for negligent design and project management lacks credibility and conviction.”  There was an allegation of defective drawings.
  • In any event the Claimants are unable to identify any drawings produced by the Defendant which caused any defective construction or any advice which was given negligently.
  • The claimants’ case on negligent design and project management “is even more threadbare”.
  • The defendant was found not to be in breach of any of the duties of care alleged.
  • In relation to the alleged design of a path “a requested design change which was never implemented could not seriously give rise to a claim in negligence.”
  • The Claimants, I consider, have done what Mr Justice Coulson (as he then was) warned against … that is to assume that any claim for bad workmanship against the contractor must automatically be reflected in a claim against the Defendant on the basis that if there is a defect, then the Defendant has been negligent for not identifying it and having it remedied…”
  • “In this case, the Claimants made little or no effort to explain what defect the Defendant should have identified the alleged defects and non-conformities and did not even put to the Defendant that she acted in breach of any duty of care in failing to identify the alleged defects and non-conformities“.
  • Some of the allegations of negligence related to matters that had occurred after the Defendant had ceased to be involved “No claim in negligence could possibly be suggested.”
  • In respect of some of the allegations the judge observed “These claims are, on any view, hopeless and no claim in negligence against the Defendant in respect of these claims should have been pleaded, let alone pursued.”
  • In relation to the Claimants’ claim for damages, which was put simply on a claim for £359,228.52 – the cost of completing the garden the judge observed:

” I consider that the Claimants could and should have attempted to identify what actual, if any, losses were suffered as a result of the breaches of alleged. To claim that the Defendant is liable for the global claim offends common sense and I find it wholly unsupported by the evidence which I have heard and read.”

“Furthermore I do not understand why the Defendant is responsible for defective works, if any, carried out by the Claimants’ contractor both before and after 9th July 2013.”

SUMMARY: THE CLAIMANTS’ WERE NOT SEEKING FAIR AND REASONABLE COMPENSATION

“To pursue this claim suggests that the Claimants seek to punish the Defendant for her alleged negligent mistakes rather than seek fair and reasonable compensation for her alleged mistakes.”

THE CLAIMANTS RECOVERED NOTHING

If anything this decision raises the issue of whether it was prudent to order a split trial in this action. The original trial was held without all the evidence being adduced. The claimants managed to establish that a duty of care was owed, the defendant then established that there was no breach of any such duty and no loss.

 

THE SUBSEQUENT DECISION IN THE COURT OF APPEAL

The case went to the Court of Appeal in 2020.  The Court of Appeal held that the claimants’ conduct of the action was such as to warrant indemnity costs.

 

The Court of Appeal decision in Lejonvarn v Burgess & Anor [2020] EWCA Civ 114 is the second time this case, about a garden, has been on appeal.   On this occasion the Court of Appeal held that the claimants’ conduct was so out of the norm as to warrant an award of indemnity costs.  The order was made on the basis of the claimants’ conduct generally and the claimants’ failure to accept an early Part 36 offer made by the defendant. There is a detailed consideration of the type of conduct that can lead to an award for indemnity costs, when the court should consider indemnity costs because a defendant’s offer has not been beaten and the relevance of the costs budget to an award of indemnity costs.

 

“There was a time, 30 or 40 years ago, when construction litigation was a byword for expense and delay, and where the costs were often out of all proportion to the sums at stake. Subsequently, thanks in part to compulsory construction adjudication, which has reduced the number of construction cases that go through to a final trial, and the careful case management by TCC judges of those cases which do, construction litigation has become a much more efficient and cost-effective method of dispute resolution. But occasionally, circumstances conspire to create a construction case with echoes of the bad old days. Unfortunately, this is one such case.”

THE CASE

This case has been looked at several times on this blog. The claimants alleged that the defendant had been negligent in the design of their garden and brought an action.  There was a preliminary trial on the issue of whether the defendant, who was providing services gratuitously, owed any duty of care. It was held that she did, that finding was upheld by the Court of Appeal. However at the trial on substantive issues the claimants failed badly. They recovered no damages.  That decision is examined here. 

THE ISSUE OF COSTS OF THE TRIAL

In March 2019 I stated that the costs decision in the case “is probably one that should be shown to all litigants”.  The claimant rejected an offer of £25,000 and failed to beat that offer at trial.   The defendant’s budget was £724,265.63 excluding VAT and the costs of preparing the budget. “This has proven to be a very expensive garden.”

THIS SECOND APPEAL TO THE COURT OF APPEAL

The claimants’ failed outright. They had rejected a Part 36 offer.  The trial judge awarded the defendant her costs, but on the standard basis. The issue before the Court of Appeal was whether the judge should have awarded the defendant indemnity costs.  Lord Justice Coulson gave the judgment of the Court. He considered the background and reviewed the authorities in relation to indemnity costs in detail.

    1. As I have already said, there can be no issue with the judge’s conclusions that the respondents’ conduct both in relation to the pre-action period and in relation to the non-compliance with the pre-action protocol does not amount to conduct which is out of the norm. I take the same view in relation to the specific matters that were raised by the appellant in relation to the conduct of the litigation itself, summarised at paragraph 30 above. These events were all a product of the way in which this litigation was fought on both sides, and the judge’s refusal to apportion particular blame one way or the other for those matters was a matter for his discretion. No error of principle in the judge’s approach is disclosed.
    2. There is, however, much more force in the appellant’s over-arching point about the judge’s failure to address the speculative/weak nature of these claims. As noted above, at [20] and [23] of the costs judgment, the judge seemed to approach the merits issue on the basis that, because there had had to be a trial in order for the lack of merit in these claims to be finally determined, there was no entitlement to indemnity costs. He appeared to consider that an order for indemnity costs was only appropriate where it could be shown with hindsight that costs had been unnecessarily incurred. I do not accept that this was the right approach as a matter of principle. Indemnity costs are, for example, routinely ordered in favour of a vindicated defendant when allegations of fraud are dismissed at trial. Obviously, there are many cases in which the strength of one side’s position, or the flaws in the other side’s case, only become apparent at trial: Bank of Ireland v Watts [2017] EWHC 2472 (TCC), to which the judge referred, was just such a case. But that is a different point: in that case, the claims themselves could not be described as prospectively weak or speculative.
    3. In addition, although the judge was referred in the written submissions to Excelsior and Three Rivers, during oral argument it appears that he was asked to focus primarily on whether the claims could be said in hindsight to be ‘hopeless’, rather than whether they should have been seen by the respondents at any time prior to the trial as speculative or weak. Contrary to Mr Oram’s post-hearing note, I consider that there is a substantive difference between the two formulations.
    4. None of that should be regarded as a criticism of the judge. It is quite clear that the essential focus of Mr Flannery’s submissions was to ask the judge to conclude that, in hindsight, the claims were hopeless because they were all dismissed at trial, and to order indemnity costs in consequence. That may have been because Mr Oram was arguing the converse. But however that focus came about, it was misplaced: the judge should instead have been asked to consider whether, at any time following the commencement of the proceedings, a reasonable claimant would have concluded that the claims were so speculative or weak or thin that they should no longer be pursued. I note that this approach was suggested for the first time in the appellant’s supplemental skeleton argument provided a few days before the appeal, which was doubtless the result of Mr Cohen’s industry and knowledge of the authorities.
    5. It seems to me that, although this point of principle was raised late, it was undoubtedly the right question, and the judge erred in not addressing it. He was also led into error by both counsel’s focus on whether or not the respondents’ claims were hopeless. That too was not the right test. For these reasons, it is necessary for this court to consider the question posed in the preceding paragraph.
    6. In my view, for the reasons set out below, the answer to the question is plain. No later than one month after the handing down of the judgment by the Court of Appeal on 7 April 2017 (i.e. by 7 May 2017) the respondents, having had time to consider the implications of the Court of Appeal judgment, should have realised that the remaining claims were so speculative/weak that they were very likely to fail, and should not be pursued any further.
    7. First, I consider that that was the cumulative effect of the decision of Mr Recorder Nissen QC (no claim in contract, rejection of the original budget advice claim), and then the Court of Appeal judgment itself. Prior to the latter, because of the finding of a duty of care on the part of the appellant, the respondents had an arguable (if not very strong) case both in relation to design and in relation to inspection, that focused not on what the appellant had done, but on what it was said that the appellant had failed to do. The Court of Appeal’s judgment, although in one sense a modest modification of the original finding of a duty, emphasised that the duty related only to the things that the appellant had actually done, not the things which it was suggested she should have done but omitted to do.
    8. The critical impact of this change should have been only too obvious to the respondents themselves, because (as the residents) they will have known almost as well as the appellant herself how little she had in fact done. Furthermore, the detrimental effect of this change on the respondents’ case can also be tracked in two ways as the events unfolded thereafter: the amendments to the respondents’ pleaded case, and their realisation of the weakness of their own claims.
    9. Thus, in their pleaded case on design, the respondents had originally asserted that, although there was nothing wrong with the drawings that the appellant produced, she should have produced other, more detailed drawings. Once that argument (based as it was on omissions) was no longer open to them, the respondents had to create a new case which suggested that her drawings were inadequate, after all. That case plainly arose out of necessity (i.e. it was all that the respondents could say, in the light of the Court of Appeal’s judgment), rather than an objective and reasoned view of the merits (i.e. that the allegations were objectively justified).
    10. The speculative/weak nature of that design case was demonstrated for all to see at the trial: see paragraph 23 above. But the failure of a case that was diametrically opposed to that which the respondents had originally argued cannot have come as a surprise to anyone. Moreover, it was no answer for Mr Oram to say that some parts of the design case were supported by expert evidence: such expert evidence as there was did not support the claim as pleaded, did not primarily come from an architect, and was served much too late to be the basis of the amended allegations. The principal reason why the new and wholly inconsistent design claim failed was not because of the judge’s rejection of the limited, late expert evidence which supported it, but because, once the omissions claim had gone, he found that the new claim “lacked credibility and conviction”. That was in effect a finding that the new design claim had been, since its formulation in 2017, speculative/weak.
    11. There was a similar volte face in relation to the budget figure of £130,000 and the claims arising from it. As the judge noted in his judgment at [92], the judgment on the Preliminary Issues, as confirmed by the Court of Appeal, required the respondents to advance “a new and wholly inconsistent case” that the budget figure of £130,000, far from being too much (which was why the parties had fallen out in the first place), was actually too little. Again, that change of case was driven by necessity rather than the merits of the underlying allegation.
    12. Again, it can therefore have been no surprise that the claims arising out of the budget (including the global claim) failed at trial. As noted at paragraphs 26-27 above, the judge said that he could not understand how the budget claim “could be seriously maintained” [91], and that the global claim which derived from it “offends against common sense” [104]. The judge had therefore found these claims had necessarily always been speculative/weak.
    13. The inspection claim, by reference to the Scott Schedule, was also significantly impacted by the Court of Appeal’s judgment, because the appellant had done so little on site. In my view, that claim always was (and should have been appreciated by the respondents to be) speculative/weak. The respondents, as the residents of the property, would have known better than anyone that (as the joint expert eventually confirmed by reference to the photographs that the respondents belatedly disclosed) all but one of these defects were not apparent on site on or prior to 9 July 2013, when the appellant’s involvement ceased. Secondly, as the judge found at [57(ii)], the claim was in any event based on the false premise that any item of bad workmanship automatically gave rise to an allegation of negligent supervision against the appellant. The related claim for non-conformance with the Enright design was regarded by the judge at [88] of the costs judgment as being “hopeless” and a claim which he said should not have been pleaded, let alone pursued (see paragraphs 24-25 above). That finding was more than enough to trigger indemnity costs, at least in relation to these parts of the claim.
    14. In short, contrary to the new points put forward in Mr Oram’s post-hearing note, I am bound to conclude that the claims maintained and/or modified after the Court of Appeal judgment did not need a long and expensive trial for it to have been apparent to the respondents and their advisors that they were, at the very least, speculative/weak claims.
    15. I am also confident that, following the Court of Appeal judgment, the respondents were themselves aware that their claims now faced significant difficulties. Although this was not dealt with at all by the judge, this can be seen in their own Part 36 offers. Having sought £220,000 before the decision in the Court of Appeal, thereafter they were prepared to accept one fifth of that (£45,000) and, subsequently, they were prepared to take even less when they offered to accept £48,000 and just 60% of their costs. Those significant reductions in the amount that the respondents were prepared to take is, on the facts of this case, eloquent testimony to the fact that the respondents must have known that, after the Court of Appeal judgment, their claims were speculative/weak and that all that really mattered now was costs. From then on, the respondents found themselves in an absurd position, where they were incurring hundreds of thousands of pounds in costs, solely in order to try and recover some of those costs from the appellant. The respondents should have called a halt, because their underlying claims were speculative/weak, but they failed to do so.
    16. I have asked myself why, in all those circumstances, these speculative/weak claims were pursued to trial. The answer may very well lie in the judge’s comment at [108] of his main judgment: that the decision to continue was borne out of the respondents’ desire “to punish the appellant for her alleged negligent mistakes rather than seek fair and reasonable compensation for her alleged mistakes”. An irrational desire for punishment unlinked to the merits of the claims themselves is precisely the sort of conduct which the court is likely to conclude is out of the norm.
    17. In summary therefore, although the judge dealt with the specific criticisms that were made of various aspects of the respondent’s conduct of the litigation, he was at no time invited to stand back and, on the evidence before him, consider whether or not there came a time when the respondents knew or ought to have known that their claims were speculative/weak and therefore likely to fail. That was the relevant question. For the reasons that I have given, I consider that, if he had asked himself the question, the judge would have concluded that such a time came not later than one month after the Court of Appeal judgment (namely by 7th May 2017). It was, in my view, out of the norm for these respondents to continue to pursue the appellant with these speculative/weak claims, each of which the judge himself described in very similar terms, beyond that date.
    18. Accordingly, if my Lady and my Lord agree, I would allow the appeal in relation to the conduct of the respondents. For the reasons that I have given, I consider that the pursuit of these claims from 7 May 2017 onwards was out of the norm such as to justify an order for indemnity costs.

INDEMNITY COSTS WHEN A DEFENDANT BEATS THEIR OWN PART 36 OFFER

The judgment goes on to give a very careful and nuanced consideration of when indemnity costs should be awarded when a defendant beats their own Part 36 offer. The right to indemnity costs is not automatic. The rules deliberately differentiate between a claimant’s and defendant’s Part 36 offer.   The question is whether the claimant’s conduct takes the matter “out of the norm”.

7. ‘OUT OF THE NORM’: THE FAILURE TO BEAT THE PART 36 OFFER
    1. Although I have concluded that the pursuit of these speculative and weak claims justified an award of indemnity costs from 7 May 2017 onwards, the respondents’ rejection of the appellant’s Part 36 offer remains relevant for two separate reasons.
    2. First, even if my analysis in Section 6, was wrong and the respondents’ pursuit of these claims was not on its own sufficient to justify an award of indemnity costs, their refusal of the appellant’s Part 36 offer was a separate matter which, when seen against the background of these particular claims, might justify an order for indemnity costs (as per Excelsior). Secondly, even if I was right about the respondents’ conduct, the respondents’ failure to beat the offer might be relevant to the basis of the assessment of costs between the Part 36 offer and 7 May 2017, the date noted above.
    3. As I have already indicated, prior to the appeal hearing itself, there was a good deal of debate about the absence of an automatic entitlement on the part of a defendant to indemnity costs in circumstances such as these. Mr Flannery went so far as to say in his original skeleton for the purposes of the appeal that this was “scandalous” and, on any view, “an oversight” on the part of the Rules Committee. In my view, the making of these colourful submissions ended up blinding both Mr Flannery and the judge from the real position.
    4. Those submissions about the Rules were misconceived. Part 36 has always been designed to provide that a claimant who beats his or her offer has an automatic entitlement to indemnity costs (unless that can be shown to be unjust) whilst a defendant has no such automatic right. Although some commentators consider this misalignment to be unjustified, it is right to note that Part 36 has been the subject of detailed consideration and amendment on at least two occasions since it was first drafted, and at no stage has it been thought appropriate to adjust this misalignment. Indeed, when the issue was the subject of specific consultation in 2006, there were mixed views as to whether or not the position of a defendant should be brought into line with that of a claimant[2] and no changes were made.
    5. Thus, as things presently stand, the CPR is clear. There is no automatic entitlement on the part of a defendant to indemnity costs if that defendant beats its own Part 36 offer.
    6. In the course of his oral submissions, Mr Cohen put this argument in a more nuanced fashion. He said that, following the more recent changes to the CPR, and in particular the renewed emphasis on proportionality, this court should conclude that there was now a presumption in favour of a defendant who beats his or her own Part 36 offer that they should be entitled to indemnity costs, or that in some way, a defendant’s beating of its own offer should be given “a pre-eminent status” in any claim for indemnity costs.
    7. I agree that the changes to the CPR in respect of proportionality are important. Their effect has been neatly summarised by Marcus Smith J in Bohinc v Malmsten [2019] EWHC 1386 (Ch) as follows:

“49. It is worth considering the role of proportionality before the new rules were introduced. The approach that the courts took was described by Lord Woolf MR in Lownds v. Home Office:

‘…what is required is a two-stage approach. There has to be a global approach and an item-by-item approach. The global approach will indicate whether the total sum claimed is or appears to be disproportionate having particular regard to the considerations which [CPR 44.4(3)] states are relevant. If the costs as a whole are not disproportionate according to that test then all that is normally required is that each item should have been reasonably incurred and the cost for that item should be reasonable. If on the other hand the costs as a whole appear disproportionate then the court will want to be satisfied that the work in relation to each item was necessary and, if necessary, that the cost of the item is reasonable. If, because of lack of planning or due to other causes, the global costs are disproportionately high, then the requirement that the costs should be proportionate means that no more should be payable than would have been payable if the litigation had been conducted in a proportionate manner. This is turn means that reasonable costs will only be recovered for the items which were necessary if the litigation had been conducted in a proportionate manner.’

50. In other words, the proportionality of the overall bill claimed determined the rigour of the subsequent assessment of costs. If the costs were proportionate, then the costs judge would simply need to consider whether each individual item was reasonably incurred at a reasonable cost. If the costs were disproportionate, on the other hand, then a higher (necessity) standard was used. Only if that cost item was necessary would the reasonable costs of that item be allowed. If the incurring of a cost was necessary, and the amount itself reasonable, there was no further ability to reduce the overall costs bill by reference to proportionality or, indeed, any other measure. The final bill could remain disproportionate to the matter at issue.

51. The present rules are very different. It is quite clear, from the express wording of CPR 44.3(2)(a) that there may be a reduction in costs on grounds of disproportionality even if those costs were reasonably or necessarily incurred.”

    1. I accept, therefore, that a claimant in the position of these respondents, unless there is an order against them for indemnity costs, will be entitled to take all sorts of points as to the proportionality of the costs incurred by the appellant which would not have been available before the rule changes. But I think it goes much too far to say that, in some way, this would disincentivise a claimant from accepting a Part 36 offer because, as Mr Cohen put it, “it reduces the stick element in failing to accept an offer”. The recent changes might reduce the ultimate amount of the defendant’s costs payable by a losing claimant, but it is hardly likely that the possibility of arguing for such reductions would amount to a cogent reason why, months if not years before those costs were even incurred, a claimant would reject a defendant’s otherwise reasonable Part 36 offer.
    2. More fundamentally, I cannot accept Mr Cohen’s submission that these changes could or should give rise to any sort of presumption in favour of a defendant who beats his or her own Part 36 offer. That seems to me to amount to a backdoor rewrite of the CPR. It would be contrary to Reid Minty, Kiam, and Excelsior. I am quite clear that the changes to the CPR in respect of proportionality do not warrant such a radical course. I therefore reject Mr Cohen’s first submission on the Part 36 offer.
    3. However, as the judge correctly noted, the absence of an automatic entitlement is the beginning, rather than the end, of the analysis. The fact that a defendant has beaten his or her own Part 36 offer is plainly a matter of importance in the exercise of the court’s discretion under CPR Part 44. The authorities repeatedly emphasise that. The question is how the judge addressed the Part 36 offer when exercising his discretion in the present case.
    4. The problem as I see it is that, having properly recorded at [26] that the respondents’ failure to beat the appellant’s offer was an important matter in the exercise of his discretion, in the very first sentence of the next paragraph of his costs judgment, the judge said that he did not think that this was a case for indemnity costs. In other words, at no point in his costs judgment did the judge say why this important factor did not, in all the circumstances of the case, lead him to exercise his discretion in favour of an order for indemnity costs or, alternatively, why an award on the standard basis was appropriate, notwithstanding the respondents’ rejection of the appellant’s early offer. It was simply not a matter that the judge addressed.
    5. When a defendant beats its own Part 36 offer, the court should always consider whether, in consequence, the claimant’s conduct in refusing that offer took the case out of the norm. Sometimes it will; sometimes it won‘t. Mr Cohen articulated the question that had to be asked in these terms:

‘At any stage from the date of the offer to the date of the outcome, was there a point when the reasonable claimant would have concluded that the offer represented a better outcome than the likely outcome at trial?’

Mr Oram agreed with that formulation orally. So, respectfully, do I. Although in his post-hearing note Mr Oram sought to qualify his agreement by reference to the offeree’s prospects of success, I consider that such a qualification is unnecessary. The important point for present purposes is that (as Mr Oram accepted at paragraph 11 of the same note), the judge was not asked to consider this question, or anything like it, and so did not do so. That was an error of law. Accordingly, I consider that this court must address the question on appeal.
    1. Again, on the facts of the present case, I consider that the answer is plain. The appellant had undertaken some work for people that she regarded as her friends, free of charge. That work took a matter of weeks. It involved one or two drawings and some visits to site. Following what the appellant saw as the respondents’ unreasonable (not to say mendacious) attitude towards the £130,000 figure which she had discussed with the first respondent not once but twice, she ceased her involvement in the garden project.
    2. Between then and the commencement of proceedings there was a good deal of acrimony. The appellant must have been all too aware of how difficult any litigation might be. Accordingly, she made an offer at the outset of the proceedings of £25,000. That offer was made just three weeks after the proceedings had started but, if it had been accepted, it would also have carried with it a significant costs liability on her part, in view of the costs both sides had incurred from July 2013 to March 2015.
    3. That offer was made for two reasons. First, it was made in the hope that the respondents would take it, so that both sides were spared the acrimony, stress and expense of litigation. But secondly, the offer was made to protect the appellant’s position on costs. If the appellant was confident that she had done nothing wrong, then the making of such an offer at the outset was the sensible thing to do. It bought her costs protection if the respondents chose to reject the offer and pursue the litigation instead.
    4. Years, and after many hundreds of thousands of pounds later, all the respondents’ claims failed. The appellant had acted sensibly and proportionately at the outset; the respondents had not. In that context, I note that the only claim which might even arguably have been said to have been untainted by the respondents’ changes of position, and/or fundamentally flawed in principle[3], was the inspection claim, which at its highest was worth just £20,000 (namely less than the appellant’s Part 36 offer in any event).
    5. Accordingly, in the particular circumstances of this case, I consider that the respondents’ failures to accept and then to beat the appellant’s Part 36 offer was a separate and stand-alone element of their conduct which was out of the norm, separately justifying an award of indemnity costs or, in the alternative, justifying such an order, when taken together with the nature of the claims pursued by the respondents.
    6. On one view, it might be said that that conclusion should lead to an order for indemnity costs dating back to March or April 2015. But, taking into account all the circumstances of the case, it is I think appropriate to limit the indemnity costs to the period after they had had time to digest the Court of Appeal judgment of April 2017[4]. It was unreasonable beyond any doubt that the respondents did not accept the Part 36 offer once they knew that their omissions case was not open to them. Accordingly, the answer to the question formulated in paragraph 80 above is 7 May 2017.
    7. I should stress that I have reached this conclusion by asking myself the questions that the judge should have been requested to ask himself, but was not, by reference to the particular facts of this case. I hope it is apparent from the previous paragraphs that I consider those facts to be relatively extreme. An order for indemnity costs was necessary and appropriate here because, on any view, this was a situation very similar to Excelsior: namely the pursuit of speculative/weak claims against the background of an offer that was unreasonably refused and subsequently not beaten.

 

THE  RELEVANCE (OR OTHERWISE) OF THE COSTS BUDGET

The judgment goes on to consider the relevance of the costs budget to an award for indemnity costs.

8 THE RELEVANCE OF THE COSTS BUDGET
8.1 Introduction
    1. However, that is not the end of the matter. Mr Oram submitted that, if this court was otherwise minded to make an order for indemnity costs, this would provide the appellant with a way round her own approved costs budget. The suggestion was that there was an approved costs budget of £415,000 whilst the appellant’s actual costs were not less than £724,265.63, so that to make an award for indemnity costs would reward the appellant for failing to keep her costs within the approved budget.
8.2 The Applicable Principles
    1. The figure produced by an approved cost budget mechanism (CPR r.3.12-r.3.18) is a different thing to the final assessment of costs following the trial. The former is prospective; the latter is retrospective. True it is that, in many cases, the approved costs budget will be the appropriate starting point for the final costs assessment. But that does not detract from the underlying proposition that they are different figures produced by different considerations with different purposes.
    2. If there is an order for indemnity costs, then prima facie any approved budget becomes irrelevant. In Denton and Others v TH White Limited [2014] EWCA Civ 906, Lord Dyson MR and Vos LJ said at paragraph 43:

“If the offending party ultimately loses, then its conduct may be a good reason to order it to pay indemnity costs. Such an order would free the winning party from the operation of CPR r.18 in relation to its costs budget””.

    1. A similar comment can be found in the more recent decision of Warby J in Optical Express Limited and Others v Associated Newspapers Limited [2017] EWHC 2707 (QB), a case where indemnity costs were ordered after a Part 36 offer had been accepted out of time. Warby J said at paragraph 52:

“52. In any case, it is legitimate to describe the claimants’ conduct as highly unreasonable and such as to justify an order for assessment on the indemnity basis. The continued pursuit of the pleaded claim after time for acceptance of the Part 36 offer expired can properly be characterised as wholly disproportionate to the value of the claim. It is fair to say that the claimants have forfeited their right to the benefit of a proportionate assessment of the defendant’s costs, and to the benefit of the doubt on reasonableness.”

    1. The absence of an overlap between the cost budgeting regime on the one hand, and an order for indemnity costs on the other, was explained in detail by HHJ Keyser QC (sitting as a judge of the High Court) in Kellie v Wheatley and Lloyd Architects Limited [2014] 5 Costs LR 854; [2014] EWHC 2886 (TCC). He said:

“17…As the passages set out in paragraph 14 above make clear, costs management orders are designed to set out the probable limits of the costs that will be proportionately incurred. It is for that reason, and not because of any quirk of drafting, that r. 3.18 refers specifically to standard assessment and not to indemnity assessment. Proportionality is central to assessment on the standard basis and it trumps reasonableness; cf. Motto v Trafigura Ltd [2011] EWCA Civ 1150per Lord Neuberger of Abbotsbury at [49]. However, proportionality is not in issue if costs are to be assessed on the indemnity basis; see r. 44.3(3). I therefore find it difficult to see why logical analysis requires importing the approach in r. 3.18 into assessment on the indemnity basis. The first reason given by Coulson J[5], at [29], has force if at all only if an approved or agreed budget does indeed reflect the costs that the receiving party says it expects to incur. However, the present case is an example precisely of the proper use of costs management in approving a budget at a lower figure than that proposed by the receiving party, on the very ground of proportionality. To suppose that the imposition of a budget under Part 3 would create some sort of presumption as to the limits of reasonable costs would be to ignore the fact that the approval of costs budgets is done on the basis of proportionality, not mere reasonableness. The matters referred to in connection with the first reason may, accordingly, justify having regard to the amount of costs the receiving party expected to incur, but they do not justify applying the r. 3.18 analogously to assessment of costs on the indemnity basis. Similarly, the second reason, stated at [30], seems to me, with respect, to go further than is justified by the costs management regime. When a costs management order is made, the parties know that costs within the approved budget are likely to be considered proportionate, and costs in excess of the approved budget are likely to be considered disproportionate; in either case, the burden of justification lies on the party seeking a departure from the approved budget. But the costs management regime is not intended to give litigants an expectation that they will not incur a liability for disproportionate costs pursuant to an order for costs on the indemnity basis; any such expectation must rest on a party’s own reasonable and proper conduct of litigation. It is no objection to an order for costs on the indemnity basis that it is likely to permit the recovery of significantly larger costs than would be recoverable on an assessment on the standard basis having regard to the approved costs budget; that possibility is inherent in the different bases of assessment, and costs on the indemnity basis are intended to provide more nearly complete compensation for the costs of litigation. I accept, of course, that a party seeking to recover disproportionate costs on an assessment on the indemnity basis is required to show that those costs were reasonably incurred; though that requirement is subject to the provisions of r. 44.3(3). That does not, however, justify the analogous use of r. 3.18, which has three disadvantages. First, it is both unnecessary and contrary to the rationale of that rule. Second, it tends to obscure the fact that the nature of the justification required of a receiving party is quite different under the two bases of assessment. Third, and consequently, it risks the assimilation of the indemnity basis of assessment to the standard basis, which is not justified by the costs management regime in the CPR. In my judgment, the proper way of addressing the concern identified by Coulson J in Elvanite at [30] is, first, by ensuring that applications for indemnity costs are carefully scrutinised and, second, by the proper application of the well understood criteria of assessment in r. 44.3(3) to the facts of the particular case. It might also be remembered that, even if there exist grounds on which an award of indemnity costs could properly be made, such an award always remains in the discretion of the court.”

  1. I respectfully agree with that analysis. In principle, the assessment of costs
    1. Before setting out briefly my reasons for rejecting Mr Oram’s submissions on this issue, I should say that, on detailed assessment, the figure for the appellant’s costs of not less than £724,000 odd is likely to be found to be unreasonable. I find it difficult to comprehend how such costs were incurred in a dispute about a garden in Highgate when the appellant’s original involvement lasted no more than a few weeks and was not the subject of charge. Accordingly, I am confident that, even on the indemnity basis from 7 May 2017 onwards, the costs finally determined on assessment are likely to be less than that figure.
    2. The first answer to Mr Oram’s submissions is that I am not persuaded that there was a clear costs management order with an approved budget figure which is a reliable comparator with the amount of costs actually incurred. There is no r.3.15 order to that effect. The best that Mr Oram could do was to show particular figures for certain future phases which O’Farrell J approved on 1 December 2017 (paragraph 15 above). However, even those figures were uncertain because her order expressly envisaged that there would be revised costs budgets. On any view, therefore, there was no clear or settled starting point as envisaged by the costs management regime. Accordingly, I am not persuaded that this is a case in which it is appropriate to compare the figure of £415,000 with the much higher figure actually incurred.
    3. Secondly, for the reasons explained in Section 8.2 above, there is as a matter of principle no overlap between a costs budget, which will have been approved on the basis of a projected series of figures for costs that were assessed as reasonable and proportionate, and the actual costs to be assessed by reference to the indemnity basis (where reasonableness might still be an issue, but proportionality is not). Thus, even if there had been an approved budget figure, it could not affect whether or not the court should make an order for indemnity costs.
9. CONCLUSIONS
  1. In my view, because these were speculative/weak claims, and/or because the respondents unreasonably refused to accept the Part 36 offer that was made early, and which they then failed to beat, this is an appropriate case for indemnity costs. In my view, the judge was not assisted by counsel then appearing, and so did not ask himself the right questions on these issues. That was the reason why he fell into error. The discretion therefore falls to be re-exercised in the way set out above.
  2. If my Lady and my Lord agree, I would order indemnity costs in favour of the appellant from 7 May 2017, being one month after the Court of Appeal judgment. The appellant’s costs prior to that date will be assessed on the standard basis.