HYBRID DAMAGES BASED AGREEMENTS: E-PETITION
There has been considerable controversy surrounding the decision not to implement “hybrid” Damages Based Agreements. There is now an e-petition calling for an open consultation on this issue. To view the petition click on the link above or here. Calls…
AN IMPORTANT CASE ON COSTS; "INTERESTED PARTY" COSTS; RELIEF FROM SANCTIONS AND SUMMARY ASSESSMENT
In Group M Uk Ltd -v- The Cabinet Office [2014] EWHC 3863 (TCC) Mr Justice Akenhead mad some important observations as to the liability to pay the costs of “interested parties”; the late serving of costs schedules; relief from sanctions…